On November 19, 2026, the MBTA announced its 2027 construction schedule. The agency anticipates 100 days of planned service outages in 2027. Most subway interruptions are scheduled for weekends. Those 100 days are planned, not guaranteed. The MBTA says the dates are subject to change because of weather, construction needs, or other factors, and that it will give advance notice, including information about shuttle buses, alternate routes, and other travel options.
WBUR reported on November 20, 2026, that the 100-day schedule is tentative, that only 34 of those days are weekdays, and that the announced work includes closures of sections of lines, not the whole system. The first half of the year, WBUR noted, includes a nine-day Green Line tunnel closure in January, a nine-day partial Orange Line closure in May, and a 10-day closure of half the Blue Line in June. General Manager Phil Eng said the agency tries to schedule around holidays and weather. “In the winters, we try to stay in the tunnels,” he told reporters after a board meeting.
Check the MBTA’s service alerts before you travel. Dates can move, and shuttle details are posted with each outage.
The work planned for 2027 includes finishing major signal upgrades on the Red and Orange lines, completing signal work in the Green Line central tunnel ahead of new Type 10 vehicles, continuing track maintenance on subway lines, and upgrading radio communications. Eng also said that in 2023, 65% of the system was found to be out of a State of Good Repair, and that work since 2024 has included replacing rail and upgrading signals.
Green Line
Symphony Station remains closed through Spring 2029 for accessibility improvements, including four new elevators and other upgrades at the 85-year-old station.
Service is scheduled to be suspended between North Station and Babcock Street on the B branch, Kenmore on the C and D branches, and Heath Street on the E branch for central tunnel signal upgrades on January 9 and 10, January 16 through 24 (nine days), February 6 and 7, February 20 and 21, and February 27 and 28. Tunnel inspections are scheduled on September 18 and 19 and September 25 and 26, on the same stretch.
Service between Reservoir and Riverside is scheduled to be suspended on August 21 and 22 and August 27 through 30 (four days) for steel repairs on the Hammond Street Bridge in Newton, which passes over D branch tracks.
Service between Government Center and East Somerville and Union Square is scheduled to be suspended November 13 through 21 (nine days) for track work. On November 13 and 14 only, that suspension is scheduled to extend to Medford/Tufts so crews can remove the Broadway Utility Bridge.
Service between Babcock Street and Boston College is scheduled to be suspended on December 4 and 5, December 11 and 12, and December 18 and 19 for accessibility upgrades at above-ground B branch stations along Commonwealth Avenue, including raising platforms eight inches above the top of the rail.
Red Line
Service between Alewife and Kendall/MIT is scheduled to be suspended January 30 and 31 for tunnel inspections.
Service between JFK/UMass and Quincy Center is scheduled to be suspended April 8 through 12 (five days) for pre-commissioning signal work. Service between Broadway and North Quincy on the Braintree Branch, and between Broadway and JFK/UMass on the Ashmont Branch, is scheduled to be suspended April 24 and 25 for more signal work and track work at switches.
Trains are also scheduled to operate on a single track between Quincy Adams and Braintree on March 26 through 28, April 2 through 4, April 9 through 11, and April 23 through 25, for signal pre-commissioning, testing, and commissioning.
Service between Kendall/MIT and JFK/UMass is scheduled to be suspended July 17 and 18 and July 24 and 25 for radio upgrades and tunnel inspections. Service between JFK/UMass and Braintree is scheduled to be suspended August 7 through 15 (nine days) for track work and work at the Furnace Brook Parkway Bridge. Trains are scheduled to operate on a single track between Alewife and Harvard on November 6 and 7 and November 13 and 14 for radio upgrades.
Orange Line
Service between Back Bay and Forest Hills is scheduled to be suspended March 6 and 7 for tunnel inspections and work on the Ruggles Station Improvements Project. Service between North Station and Ruggles is scheduled to be suspended May 15 through 23 (nine days) for track work. Service between North Station and Back Bay is scheduled to be suspended July 10 and 11 for radio upgrades, and again October 8 through 11 (four days) for construction of two new accessible transfer elevators at Downtown Crossing.
Blue Line
Service between Bowdoin and Airport is scheduled to be suspended June 18 through 27 (10 days) for track work, and again October 23 and 24 for radio upgrades.
Mattapan Line
Service between Ashmont and Mattapan is scheduled to be suspended March 27 and 28 and April 3 and 4 for track maintenance and upgrade work.
Commuter Rail
The same announcement also lists commuter rail interruptions. Weekend suspensions of all commuter rail lines operating between South Station and Braintree, and between Back Bay and Forest Hills, are scheduled for March 20 and 21 and April 3 and 4. The Worcester Line is scheduled to be suspended between Back Bay and Framingham on June 5 and 6 and June 26 and 27 for track upgrades at Newtonville. Off-peak weekday disruptions, from 9 a.m. to 3:30 p.m., are planned on the Needham Line between Forest Hills and Needham Heights from March 1 through May 21, and on the Newburyport/Rockport Line between Newburyport and Ipswich from March 8 through June 30. Service between Foxboro and Walpole is scheduled to be suspended March 19, March 22, April 2, and April 5. Work at South Station’s Cove Interlocking is scheduled to have some impacts to regular schedules on the Needham, Worcester, Providence/Stoughton, and Franklin/Foxboro lines on June 18 through 20, July 30 through August 1, August 27 through 29, September 17 through 19, and October 22 through 24. The Lowell Line is scheduled to have some impacts on November 13 and 14, when crews remove the Broadway Utility Bridge.
Because these dates can change, check the MBTA’s service alerts for the latest station-by-station notices and shuttle plans. For getting around the city when the T is limited, see our guides to why Boston traffic is so bad and Boston running paths.